Reference · D4 motorway
Cabling and telematics on the D4 near Skalka.
Cable infrastructure and technology for a new section, including integration into the ŘSD and NDIC systems.
12 photos
D4 · Skalka – II/118 junction · km 41.115 – 45.903 · 2015–2017
Skanska a.s. · Cable infrastructure + technology · Integration into ŘSD and NDIC systems
01 · The briefCable infrastructure + technology
Cable infrastructure and technology for a new section, including integration into the ŘSD and NDIC systems.
We built the Skalka – II/118 junction section for Skanska a.s. from scratch: cable trench, low-voltage lines, HDPE ducts, transverse and longitudinal crossings and the blowing-in of the OK-DIS fibre-optic cable. Then came the supply, installation and commissioning of emergency call boxes, a road weather station, traffic counters, CCTV surveillance and variable message signs, integrated into the ŘSD and NDIC systems.
Parameters
- Road
- D4 motorway
- Construction
- Skalka – II/118 junction
- Chainage
- km 41.115 – 45.903
- Length
- 4.8 km
- Client
- Skanska a.s.
- Investor
- ŘSD ČR
- Built
- 2015–2017
- Status
- In operation
02 · Scope of supply
What we delivered on site.
Cable infrastructure
supply of the complete cable infrastructure comprising:
- excavation and backfilling of the cable trench for the installations
- laying of low-voltage lines and HDPE ducts
- construction of transverse and longitudinal crossings
- blowing-in of the OK-DIS fibre-optic cable
Technology
supply, installation, commissioning and integration into the ŘSD and NDIC systems of the technology comprising:
- Emergency call boxes
- Road weather stations
- Traffic counters
- CCTV surveillance
- Variable message signs
03 · Photos from the site
From the field.












REF · D4 SKALKA · 2015–2017