Reference · D6 motorway
Technology for the Řevničov bypass on the D6.
We delivered the cable infrastructure and the technology along the whole 4.2 km of the bypass.
We delivered the cable infrastructure and the technology along the whole 4.2 km of the bypass.
For SWIETELSKY stavební we built the complete cable infrastructure on the Řevničov bypass: excavation and backfilling of the cable trench, laying of low-voltage lines and HDPE ducts, transverse and longitudinal crossings and the blowing-in of the OK-DIS fibre-optic cable. The technology followed: emergency call boxes, road weather stations, traffic counters, CCTV surveillance and variable message signs, which we supplied, installed, commissioned and integrated into the ŘSD and NDIC systems.
- Road
- D6 motorway
- Construction
- Řevničov bypass
- Chainage
- km 37.550 – 41.750
- Length
- 4.2 km
- Client
- Swietelsky stavební s.r.o.
- Main contractor
- Metrostav – Eurovia CS – Swietelsky joint venture
- Investor
- ŘSD ČR
- Built
- 2017–2020
- Status
- In operation
What we delivered on site.
Cable infrastructure
supply of the complete cable infrastructure comprising:
- excavation and backfilling of the cable trench for the installations
- laying of low-voltage lines and HDPE ducts
- construction of transverse and longitudinal crossings
- blowing-in of the OK-DIS fibre-optic cable
Technology
supply, installation, commissioning and integration into the ŘSD and NDIC systems of the technology comprising:
- Emergency call boxes
- Road weather stations
- Traffic counters
- CCTV surveillance
- Variable message signs
From the field.